Hinge Unloading Method



Your Ad Here

The Hinge Unloading Method option appears on the Nonlinear Parameters form. Access the Nonlinear Parameters form as follows:

  1. Click the Define menu > Analysis Cases command to display the Analysis Cases form.

  2. Click the Add New Case button or highlight a previously defined analysis case and click the Add Copy of Case or the Modify/Show Case button to display the Analysis Case Data form.

  3. Select Static from the Analysis Case Type drop-down list and the Nonlinear or Nonlinear Staged Construction option  for the Analysis Type.

  4. Click the Nonlinear Parameters Modify/Show button to display the Nonlinear Parameters form.

 

When a hinge unloads, the program must find a way to remove the load that the hinge was carrying and possibly redistribute it to the remainder of the structure. Hinge unloading occurs whenever the stress-strain (force-deformation or moment-rotation) curve shows a drop in capacity, such as is often assumed from point C to point D, or from point E to point F (complete rupture).

Such unloading along a negative slope may be unstable in a static analysis, and a unique solution is not always mathematically guaranteed. In dynamic analysis (and the real world) inertia provides stability and a unique solution.

For static analysis, special methods are needed to solve this unstable problem. Different methods may work better with different problems. Different methods may produce different results with the same problem. SAP2000 provides three different methods to solve this problem of hinge unloading, which are described next.

If all stress-strain slopes are positive or zero, these methods are not used unless the hinge passes point E and ruptures. Instability caused by geometric effects is not handled by these methods.

Note: If needed during a nonlinear direct-integration time-history analysis, SAP2000 will use Method 2: Apply Local Redistribution.

Hinge Unloading Method

Whether the load must be reversed or not to unload the hinge depends on the relative flexibility of the unloading hinge compared with other parts of the structure that act in series with the hinge. This is very problem-dependent, but it is automatically detected by the program.

This method is the most efficient of the three methods available, and is usually the first method you should try. It generally works well if hinge unloading does not require large reductions in the load applied to the structure. It will fail if two hinges compete to unload, i.e., where one hinge requires the applied load to increase while the other requires the load to decrease. In that case, the analysis will stop with the message "UNABLE TO FIND A SOLUTION," in which case you should try one of the other two methods.

This method uses a moderate number of null steps.

This method is often the most effective of the three methods available, but usually requires more steps than the first method, including a lot of very small steps and a lot of null steps. The limit on null steps should usually be set between 40% and 70% of the total steps allowed.

This method will fail if two hinges in the same element compete to unload, i.e., where one hinge requires the temporary load to increase while the other requires the load to decrease. In that case, the analysis will stop with the message "UNABLE TO FIND A SOLUTION," after which you should divide the frame object so the hinges are separated and try again. Check the .LOG file to see which objects are having problems. Caution: The object length may affect default hinge properties that are automatically calculated by the program, so fixed hinge properties should be assigned to any objects that are to be divided.

When the load is re-applied from the beginning of the analysis, each hinge moves along the secant until it reaches point X, after which the hinge resumes using the given stress-strain curve.

This method is similar to the approach suggested by the FEMA 273 guidelines, and makes sense when viewing pushover analysis as a cyclic loading of increasing amplitude rather than as a monotonic static push.

This method is the least efficient of the three, with the number of steps required increasing as the square of the target displacement. It is also the most robust (least likely to fail) provided that the gravity load is not too large. This method may fail when the stress in a hinge under gravity load is large enough that the secant from O to X is negative. On the other hand, this method may also give solutions where the other two fail due to hinges with small (nearly horizontal) negative slopes.

Example

Consider the frame with two pushover hinges shown below:

 

The force deflection characteristics of the two hinges are illustrated below:

When the pushover analysis is run, it turns out that pushover hinge 2 passes point E (i.e., unloads twice) before pushover hinge 1 reaches point C and begins to do any unloading.

The pushover curve using the Restart Using Secant Stiffness option is shown in the figure below. The pushover curve is made up of five separate curves. Curve 1 ends when pushover hinge 2 reaches point C and the structure must drop load. Curve 2 ends when pushover hinge 2 reaches point E and the structure must drop additional load. Curve 3 ends when pushover hinge 1 reaches point C and Curve 4 ends when pushover hinge 2 reaches point E. Curve 5 ends when the displacement target is reached. Note that since a mechanism has occurred, curve 5 is just a flat line along the X-axis.

 

The following ten figures show the loading and unloading paths taken by pushover hinge 1 and pushover hinge 2 for each of the five components of the pushover curve.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Return to SAP2000 Index


Your Ad Here